Arup Experience

A120 Braintree to A12, UK, 01/2022 – 04/2022

Client: National Highways

Phill was the Drainage Design Lead responsible for the design of the highway drainage systems associated with the proposed scheme between Braintree and the A12. The scheme is currently at stage DF1, which requires an outline design consisting of key drainage design features such as balancing ponds and culverts under the mainline carriageway.


High Speed 2, Phase 2a ACD Scheme, UK, 10/2021 – 05/2022

Client: HS2 Ltd

Phill was the Drainage Technical Discipline Lead within an integrated JV team responsible for the design of all drainage systems associated with the HS2 Phase 2a Advanced Critical Design (ACD). This project was split into tasks, where Drainage input is required for 4 out of 8 tasks. Responsibilities include for the “Scheme Design” of a 10km section of open route, which involves understanding the detailed design of track drainage to ensure full coordination with earthworks, track systems and noise fencing. Working with Network Rail as a partner, a GRIP3 drainage design for the existing WCML corridor is also being developed to provide a more resilient and sustainable drainage system. In addition, the layout of the tunnel portal areas include for associated drainage works, such a pumping station compound, potable water firefighting supply tank and contaminated water holding tank.


HS1 Tunnels, UK, 01/2022 – 04/2022

Client: Network Rail High Speed

Phill was the Drainage Design Lead responsible for the design of the tunnel drainage system associated with an on-going issue of groundwater entering the tunnel through displaced joints and failed grout plugs. The solution was to be simple, cost efficient and be flexible to apply to other areas of the tunnel, where required. After an assessment of several options, the final solution was to provide saw cut channels in the concrete walkway, leading to a narrow channel affixed to the vertical wall; which discharges into the central drain under the rail tracks.


A120 bypass (Little Hadham) and flood alleviation scheme, UK, 09/2021 – 11/2021

Client: National Highways

Phill supported the on-site design team with some drainage design changes which were required following detailed site investigation returning infiltration rates less than originally designed for. The initial drainage design associated with an underpass under the newly constructed A120 mainline consisted of deep bore soakaways and geocellular attenuation tanks. As much of this solution had already been constructed it was necessary to find a solution that utilised this system as far as practicable. After testing several options including for a pumping station, additional storage and additional deep bore soakaways, the final solution involved the reassessment of the design parameters which resulted in amending the runoff coefficient used for the cutting slopes. By demonstrating that the constructed design was sufficient to meet the Local Authority requirements, the final design was approved; saving the project approximately £150,000 and avoided any risk with meeting the programmed opening date.


High Speed 2, Phase 2a ERD+ Scheme, UK, 09/2020 –10/2021

Client: HS2 Ltd

Phill was the Drainage Technical Discipline Lead within an integrated JV team responsible for the design of all drainage systems associated with the HS2 Phase 2a ERD+ Scheme. Deliverables included hydraulically designed 3d pipe models and asset tagged design data. Significant cost savings have been made by optimising the drainage design, which has reduced the volume of engineering earthworks required across the Scheme. Working with Network Rail as a partner, a GRIP3 drainage design for a realignment of the WCML has also been delivered.


East West Rail, Central Area, UK, 02/2020 –12/2020

Client: East West Rail Co.

Phill was the Drainage Technical Discipline Lead responsible for the design of all drainage systems associated with Central Area of the East West Rail project. He was responsible for setting out the approach and technical standards that are to be used throughout the project, covering railway drainage, highway drainage and land drainage. Working on several options under development, it was necessary to find efficiencies in working methods such as using digital automation and providing a sufficient level of detail to undertake an appropriate assessment.


M42 Solihull MSA, UK, 12/2019 – 06/2020

Client: Extra

Phill was the Lead Drainage Engineer responsible for reviewing drainage design proposals, implementing any amendments and assuring the design by undertaking hydraulic modelling using specialist software. He also supervised drainage drawing production and produced a drainage design report to obtain approvals from Highways England.


High Speed 2, Phase 2b Scheme, UK, 09/2017 – 06/2020

Client: HS2 Ltd

Phill was the Drainage Technical Discipline Lead responsible for the design of all drainage systems associated with the HS2 Phase 2b (Lot 3) Scheme. He managed a team of up to 18 people, responsible for the design of railway drainage, highway drainage, station drainage, depot drainage and land drainage. He had a budget of approximately £1.5m for design fees from inception to the deposit of the hybrid Bill. The capital cost of the drainage works is approximately £50m. Additional duties included for value management, where in March 2019 a project cost saving of approximately £23m was realised by changing the railway drainage design solution.


High Speed 2, Phase 2a ERD Scheme, UK, 04/2018 – 12/2019

Client: HS2 Ltd

Phill was a Drainage Technical Reviewer for the Employer’s Requirements Design of HS2 Phase 2a. His duties included for undertaking design reviews and offering advice to the design team. ERD drainage works include for hydraulic pipe modelling, 3d pipe modelling and asset tagging. 

 

High Speed 2, Phase 2a Scheme, UK, 11/2016 – 12/2019

Client: HS2 Ltd

Phill was the Lead Engineer responsible for the design of track drainage, perimeter drainage, highway drainage and depot drainage. His duties included for producing detailed hydraulic calculations, CAD drawing models, coordinating with other disciplines, input into design reports and managing team workload. This role developed into a Technical Discipline Lead role due to previous Leads leaving the project which gave him additional responsibilities for managing a team, budgets and ensuring a compliant design was delivered for final approval.


High Speed 2, West Midlands Metropolitan Area, Hybrid Bill Design, UK, 09/2015 – 10/2016

Client: HS2 Ltd

Phill was the Lead Engineer responsible for the Employers Requirement Design of track drainage throughout the Birmingham Metropolitan Area. Duties included detailed hydraulic modelling, report writing and managing drawing production. As part of this work, he developed the hybrid Bill design further to include for on-line storage within the railway drainage system, so that balancing pond volumes and associated land take areas could be reduced.


A602 Improvements, UK, 05/2015 – 04/2016

Client: Hertfordshire County Council

Phill was the Lead Engineer responsible for the highway drainage design of a section of the A602 improvement works in Hertfordshire. Duties included high level hydraulic modelling, report writing and managing drawing production. Additional tasks included the outline design of a single lane dualling option at a junction, contributing to a watercourse crossing assessment and assisting with the design of a new junction.


M4 Corridor around Newport, UK, 05/2015 – 08/2015

Client: Welsh Government

Phill was an Engineer responsible for the highway drainage design across a large bridge crossing the River Usk. Duties included detailed hydraulic modelling, report writing and managing drawing production. Additional tasks included producing a designer’s risk assessment for a proposed open channel/swale and preparing an optioneering study to identify preferred surface water drainage outfall points.


Entec/Amec Experience


The Avenue SuDS Channel Design, UK, 01/2012 – 04/2015

Client: VSD Avenue/Homes and Communities Agency

Phill was the Lead Engineer responsible for the detailed design of a sustainable drainage system consisting of two-stage trapezoidal channels, two cascades, two weirs and a pipe culvert. Private pipe connections were also designed to allow off-site flows to enter the channel. A ground model was updated to suit the design levels which included for a large wetland area and redesign of a river channel. The delivery of information included a series of construction drawings and a drainage strategy that was approved by the Environment Agency first time, which saved time in the construction programme.


Greengairs MBT, UK, 04/2014 – 09/2014

Client: FCC Environment

Phill was Lead Engineer responsible for discharging a Planning Condition in relation to providing full details of the surface water drainage scheme on a proposed Mechanical Biological Treatment (MBT) facility. As the site is based in Scotland, close liaison with the Scottish Environment Protection Agency (SEPA) was required to ensure that the final solution would meet their strict criteria. The solution consisted of three management trains in areas where potential pollution incidents were high risk, which included for dry swale along the perimeter boundary, an attenuation lagoon and wet swale prior to final discharge. This ensured that the water quality entering the local watercourse was acceptable to SEPA. As the site was in detailed planning, it was necessary to fully understand how the system operate and therefore the design accounted for ground levels, site constraints and materials used.


Thriplow Peat Holes SSSI, UK, 03/2012 – 09/2012

Client: Environment Agency

Phill was Project Manager and Lead Engineer for the relocation of a rising main and outfall within a SSSI. Responsible for the design of the works, the financial management and management of a specialist within another office. To avoid the need to affect the SSSI in any way a directional drilling technique was proposed to lay the new pipe. The client was highly supportive of using this technique as it would ensure that wildlife and the woodland was left unaffected by the construction works. A new set-back outfall was designed to dissipate the pumped flows by including for a rock gabion mattress filled with rushes and reeds. Other duties included for undertaking the role of ECC-PM/Supervisor during the construction works to ensure that works were completed to the specification, on time and within the budget.


MoD Bicester Planning Support, UK, 08/2011 – 03/2012

Client: Defence Estates

Phill was Lead Engineer responsible for the delivery of a drainage strategy for large scale mixed development sites in Bicester garrison, known as C Site and Graven Hill. The strategies included for both foul water drainage and surface water drainage, where sustainable drainage systems (SuDS) were incorporated into the detailed masterplan to add considerable amenity value to the final scheme.

Site constraints such as steep contours and soils underlined with clay caused many design challenges in the development of the surface water strategy. During the design process the Environment Agency gave approval in principle and were anticipating an exciting and sustainable drainage system as part of the planning submission.


Deepcut Outline Planning Application, UK, 06/2012 – 12/2012

Client: Defence Estates

Phill was Lead Engineer on the production of a drainage strategy to accommodate a proposed mixed use development covering a total area of 114ha. Responsible for the design of a sustainable drainage system (SuDS) in line with the latest National Planning Policy Framework and Flood & Water Management Act 2010. The design included for infiltration at source, conveyance swales and attenuation ponds to ensure the quantity and quality of flows entering the SSSI Basingstoke Canal were controlled to an acceptable standard. Working closely with the master planning and landscape design team the design was integrated successfully and without any removal of existing woodland.


Project Wellesley, UK, 10/2012 – 04/2015

Client: Defence Estates

Phill was Lead Engineer responsible for the delivery of a drainage strategy and utility strategy for an outline planning application at the Worthy Down MoD Camp and Service Family Accommodation (SFA). The application included for the replacement of existing buildings within the Camp and the inclusion of up to 90 houses in the SFA, which resulted in an increase in surface water flow, foul water flow and utility demand requirements. The surface water strategy included for sustainable drainage systems (SuDS) such as infiltration and conveyance techniques. There was a need to divert and lay new foul drainage networks across the new site layout and was also a need to assess and discuss utility demand requirements with the relevant suppliers.


PICP Support to Cable and Wireless Worldwide, UK, 03/2010 -05/2011

Client: Cable and Wireless Worldwide

Following certification to ISO 14001 in February 2011, C&WW identified sites across the UK with fuel storage above 10,000 litres that required site specific Pollution Incident Control Plans (PICP's).

The PICP informed site users and visitors of the key actions and responsibilities to prevent and respond to a pollution incident.

Phill’s key responsibilities included visiting site to undertake a visual survey of the equipment and storage facilities in order to produce an accurate plan. In addition to the production of the PICP's, the on-site drainage systems were surveyed by lifting manhole covers and recording the pipe details such as diameter, levels and condition. A high level model was produced using MicroDrainage software to assess the potential risk of flooding on site under common storm conditions.


Bates Colliery S278 Works, UK, 03/2010 – 08/2010

Client: Banks Property

Phill was Lead Engineer responsible for the production of a highway widening and bus lay-by design to meet all requirements under a S278 agreement. The package included horizontal and vertical design, finished road level contour design and standard detail production, along with a detailing works specification. Other duties included the management of a street lighting design and close liaison with utility companies to understand diversion requirements.


North Bingham Outline Planning, UK, 03/2009 – 09/2009

Client: Rushcliffe Borough Council

Phill was Lead Engineer responsible for the delivery of a utility assessment for a proposed 237ha mixed use development, including 2,500 homes. The purpose of the assessment was to identify the main utility constraints which could affect the development aspirations. This involved identifying routes of utilities as well as understanding the current performance, condition and capacity. The proposed loadings were calculated and discussed with the providers to understand any upgrade requirements and cost of connections.


Wood Green High School, UK, 06/2008 – 11/2008

Client: Haringey Council

Phill was Lead Engineer responsible for the production of a mini roundabout design to meet all requirements under a S278 agreement. Design included provisions for a safe route to school by introducing zebra crossings. Working with limited assistance the package included horizontal and vertical design, finished road level contour design and standard detail production. Attended design meetings with the client to provide progress reports and to gather comments that could be fed back into the design. Also responsible for providing a designers response to a road safety audit for the proposed works.


Harwell Nuclear Site Decommissioning, UK, 06/2007 – 06/2008

Client: UK Atomic Energy Authority (UKAEA)

Phill was Lead Engineer for the de-licensing of UKAEA Harwell nuclear licensed site via decommissioning of legacy services and structures remaining from an active civil nuclear research facility. Responsible for the delivery of decommissioning, as-built drawings and associated risk assessments to the satisfaction of the Health Protection Agency (formally the National Radiological Protection Board), the Nuclear Installations Inspector, and more recently the Nuclear Decommissioning Authority. Other duties included site supervision during construction works and sewer modelling to test against flood risk.



Southern Water Secondment, UK, 06/2006 – 12/2006

Client: Clancy Docwra/Southern Water

Phill provided Clancy Docwra with design support for their client, Southern Water. This work was part of a Customer Focus Sewage Challenge and required design knowledge of sewage systems. Working closely with Clancy Docwra providing quick and efficient designs for relaying or realigning poor drainage. The work was fast paced as a design and build contact, requiring a good working relationship with both the contractor and the client.

Share by: